Council is pleased to announce the commencement of its 2024-25 water main replacement program, which will help improve water infrastructure across multiple streets in the local area. The project is part of ongoing efforts to enhance the reliability and sustainability of our water network. Works will take place over several months, with specific streets scheduled for replacement between November 2024 and September 2025.
Program details:
Where | Duration | Dates |
Rupert Street | 26 Days | 11 November 2024 to 16 December 2024 |
Margaret Street (Chantilly Street to Whitton Street) | 12 Days | 27 January 2025 to 11 February 2025 |
Whitton Street (Margaret Street to Elizabeth Street) | 15 Days | 12 February 2025 to 4 March 2025 |
Jonsen Street (Mitchell Street to Whitton Street) | 13 Days | 5 March 2025 to 21 March 2025 |
Arthur Street (Whitton Street to King Street) | 18 Days | 24 March 2025 to 16 April 2025 |
Elwin Street (Adams Street to East Street) | 31 Days | 17 April 2025 to 29 May 2025 |
Twynam Street (Adams Street to East Street) | 31 Days | 30 May 2025 to 29 June 2025 |
Bolton Street (Beckham Street to Adams Street) | 31 Days | 14 July 2025 to 25 August 2025 |
Adams Street (Douglas Street to Tynam Street) | 20 Days | 26 August 2025 to 22 September 2025 |
Why is this important?
Replacing these water mains will help ensure a more resilient and efficient water network for the community, reducing the risk of disruptions in service and enhancing the quality of the water supply.
For more information:
For further details on specific dates or to inquire about how the project may affect you, please contact council's Water Sewer Project Engineer on 02 6959 5510 or email council@narrandera.nsw.gov.au.