Council's 2024-25 Water Main Replacement Program - Key Dates and Impact

Council is pleased to announce the commencement of its 2024-25 water main replacement program, which will help improve water infrastructure across multiple streets in the local area. The project is part of ongoing efforts to enhance the reliability and sustainability of our water network. Works will take place over several months, with specific streets scheduled for replacement between November 2024 and September 2025.

Program details:

WhereDurationDates
Rupert Street26 Days11 November 2024 to 16 December 2024
Margaret Street (Chantilly Street to Whitton Street)12 Days27 January 2025 to 11 February 2025
Whitton Street (Margaret Street to Elizabeth Street)15 Days12 February 2025 to 4 March 2025
Jonsen Street (Mitchell Street to Whitton Street)13 Days5 March 2025 to 21 March 2025
Arthur Street (Whitton Street to King Street)18 Days24 March 2025 to 16 April 2025
Elwin Street (Adams Street to East Street)31 Days17 April 2025 to 29 May 2025
Twynam Street (Adams Street to East Street)31 Days30 May 2025 to 29 June 2025
Bolton Street (Beckham Street to Adams Street)31 Days14 July 2025 to 25 August 2025
Adams Street (Douglas Street to Tynam Street)20 Days26 August 2025 to 22 September 2025

Why is this important?

Replacing these water mains will help ensure a more resilient and efficient water network for the community, reducing the risk of disruptions in service and enhancing the quality of the water supply. 

For more information:

For further details on specific dates or to inquire about how the project may affect you, please contact council's Water Sewer Project Engineer on 02 6959 5510 or email council@narrandera.nsw.gov.au. 